Machine Checkout for injection test (updated for 2009)

Injection etc:  Brennan's list

Controls

Full list

Verify:

Interlocks

Beam Instrumentation

Power Converters

Full functionality of digital controllers plus world FIP, gateways, network
Standard high-level control functionality: cycle, ramp, set, trim, alarms, interlocks, states, tolerances
Acquisition: debugging, tracking studies...
Appropriate handling of nested power supplies

Collimators etc

Septa

power converter, controls, interlocks

Kickers

Controls, timing, pre-pulses, analogue acquisition

Radiation Monitoring

Acquisition, displays, logging

RF
Pre-pulses, low level control [cavity control, synchro, beam control, longitudinal damper], transverse damper, power systems. Diagnostics.
Synchronisation with injectors

Beam Dump
timing, post-mortem, inject and dump

 

Settings etc.
calibrations, optics, transfer functions, ramp, squeeze…
Radiation monitoring
Access system
INB, EIS
Operation
Experiments
Data interchange
Beam aborts

 

Magnets

 

Ramp tests of all available circuits in collaboration with AB/PO. Implies availablity of QPS, PIC and PM etc.

Errors: all circuits, full cycle
geometric, beam screen, saturation
eddy,
RMS/Persistent currents
static model
powering history dependent model
on-line reference magnets
Cycle path – all magnets
Transfer functions
for all magnet circuits
hysteresis behaviour for corrector circuits where appropriate
Strategy for:
excitation of nested correctors
cycling nested pc/magnets