LHC Sector Test meeting held on 06-04-2004 

Subject: Access system requirements during sector test

Present:  Roger Bailey, Mike Lamont, Jan Uythoven, Pierre Ninin, M.G., Juget, Ghislain Roy, Felix

Presentation covering the main issues [pdf

Summary:

For Sector 8-1, PM76, PM85, PZ85, Sector 6-7:

- Ensure that test zone is inaccessible while possibility of beam
- Interlock beam off if above conditions are broken
(access system will interlock TI8 main bends, TED in, will not directly inhibit extraction from SPS)
- Ensure the test zone is inaccessible until a radiation survey is performed
- Allow limited controlled access during and after the test

Issues:

Installation
Gates – allow 2 days, who is responsible for pulling the cables? Work in parallel of course.
Pilot application tests – 5 days, need to see all signals . (HWC provides some opportunity but only looks for electrical hazards etc., sector test needs to check machine EIS)
DSO test – 1 day, need standard configuration, force all 5 doors in turn and verify.
4 days with machine shut to fully commission.

Emergency stop? Should be hooked up if final system is in place. Check this. Are they hooked to the access system?
CSAM? Nothing specific to sector test


Re-commissioning TI8
Will have to be done as an integral part of the sector test, can not envisage establishing sub-zone.
TT40, on the other hand, should be possible with zones already defined.

Decommissioning procedure:
Radiation survey will be performed before removal of gates
Get the gates out – 2 days
Get the dump out. Need prior authority for transport of dump.

Formalities
Have to establish prior authority, and what measures will be in place. Should be an addendum to the big report going to INB in summer 2005 (?) where final go ahead for LHC and sector test will be given.
A safety handbook for the project would be desirable.
Report to be prepared (Ghislain, Mike…). Remind Ghislain frequently.