1st Phase

Weekend 26/27 July - evacuation tests.

Saturday: Strapping of signals. Start tests.

Sunday: - EIS offline. Reconfigure access system - simulation boxes except RF.

Machine patrolled by Monday evening - Katy

2nd Phase

Week 31 - every eveing - intrusion tests with whole machine closed. Emergency access if required. From 17:00

Start Monday evening - team of 20 going in. Quite a few patrols to do.

Restricted access everyday - respect doors Guards at top of pit - entry by cards - to ensure restricted access is maintain, and avoid heavy load on CCC.

Day stand-by Patrol 29 Jul - 4 Aug

3rd Phase

M & T Tuesday Continue evacuation tests, put EIS in chain and test

 

6 & 7 - Patrols in machine

Beam injection on 9/10 August

 

Last 3 days impact HWC