Who |
|
|
|
|
|
Commission injection region: beam 1, 1 pilot |
|
|
System |
Software |
|
|
Injection preparation (SPS, TLs, timing, close TDI) |
|
|
|
|
|
|
Commission final 100 m of TI 8 |
|
|
|
|
|
|
Setup injection elements and beam to TDI |
|
|
|
|
|
|
Beam commissioning injection BTVs |
|
|
BTV |
Standard application - on-line, off line fits to beam sizes |
|
|
Detailed steering onto TDI |
|
|
Steering |
YASP |
|
|
Power injection kicker MKI, beam to TDI |
|
|
Kickers |
LSA |
|
|
Check stability of transfer lines and trajectory without MKI |
|
|
BPM - capture |
|
|
|
Check stability of injected
trajectory with MKI on, measure MKI waveform |
|
|
MKI - logging |
|
|
|
Beam commissioning SIS system (parasitic) |
|
|
SIS |
|
|
|
Perform aperture scan at MSI |
|
|
- Bumps
- Local beam loss
- BCT |
|
|
|
Threading around the ring: beam 1 |
|
|
|
|
|
|
Open TDI and inject into ring |
|
|
TDI Controls |
- Collimator control
- Settings |
|
|
Coarse beam commissioning of BPMs (asynch. acquisition) and
BLMs |
|
|
- BPMs
- BLMs |
- Acquisition, concentration
- Display |
|
|
Commission trajectory acquisition and correction |
|
|
- BPM "threading"
- trajectory correction |
YASP |
|
|
|
|
|
- ditto - |
|
|
|
First measurement of energy mismatch (correction if needed) |
|
|
- BPMs - capture |
- momentum trim SPS/TI8/LHC
- YASP - calculate deltap per arc |
|
|
First BPM and corrector polarity checks and repairs |
|
|
- kicks
- BPM capture |
- sliding bumps |
|
|
Commission BPM intensity measurement mode (parasitic) |
|
|
BPM intensity mode |
|
|
|
Systematic BPM and corrector polarity checks and repairs |
|
|
- kick |
loop: kick, measure |
|
|
Systematic physical aperture scans, free oscillations and
sliding bumps |
|
|
BLMs, BPMs, FBCT |
sliding bumps, kicks |
|
|
Systematic linear optics checks with kick/response |
|
|
|
loop: kick, acquire, YASP |
|
|
Momentum aperture measurement |
|
|
|
|
|