RADIATION ISSUES
For overview of radiation issues see presentation to RPC (5/12/2003) and to INB Paris (November 2005)
Clearly access has to be prevented to the tunnel within given boundaries whilst beam tests are in progress. Thereafter the we must anticipate the remnant radiation doses and the appropriate precautions that must be taken after the test. These precautions depend on the remenant dose levels, see radiation areas below.
Input courtesy of Graham R. Stevenson, Doris Forkel-Wirth, Stefan Roesler & Helmut Vincke.
1) How many protons of the LHC beam will be absorbed by the spoiler in LSS4 of SPS (for CNGS: 0.1 - 0.5 % of the beam). This number might determine the dose rate in ECA4 where the shielding wall is not yet finalised in 2006.
Should of course be very low, however, worst case would be occasionally
losing a few bunches with kicker problems (timing, strength, missing) so 0.1 %
average loss would be reasonable. (CNGS commissioning more of an issue...)
2) How many protons will be send on the TED at the end of TI8
3) Do we have any idea how many protons we will loose at the collimator?
4) How many protons (in percent of the beam do we loose in LHC-b (for dose rate estimates for counting rooms of LHC-b)
Large aperture - un-squeezed optics - no crossing angle. Not more than
1% of total (therefor around 3 e11). Would be very careful about switching
on
crossing-angle
bumps
and injecting into different bumps. Could possibly mis-steer beam into LHCb during
initial commissioning, so say 5 e11 total.
5) How many protons on the final TED
We estimate 2.7 e13, rounding up to 3 e13 would be fine - this more or
less evenly distributed over a 2 week period
6) distance between TED in Point 7 and entrance to TZ 76
UJ76 is 33.88 m from IP7, spans around 22 m of the tunnel and sits next to the two TCS upstream (nearer IP7) of Q4.
Approximately 135 metres between dump and start of UJ76
RPG have taken case 3 shown in the table below as their maximum for the sector test. This scenario represents an extreme case. At these intensities: the dose rates for 1 day irradiation and 1 day cooling following a proton intensity of 1.5 1010 ps-1 (50% efficiency - case 3) are given below at the dump and in the arcs. This dose totals 1.3 1015 protons in 24 hours.
It is estimated that during the test around 3 x 1013 protons will be used over a 2 week period. Thus the figures below can be scaled accordingly (see latest presentation).
C/o Doris
In 2003 we made very conservative first extrapolated predictions for the TED activation for the sector tests:
Therefore I suggest that we stick to:
These figures are somewhat higher initially due to the short-lived activation of the concrete walls along side the dump. Effects confirmed by measurements following the TT40 tests (see presentation above).
Assume beam is lost uniformly along the sector between point 8 and point 7
Assume beam is lost repeatedly in one dipole (unlikely scenario)
With the un-scaled dose rates:
Case | Proton Intensity | Period [s] | pps - rounded | fraction | TED punch-through s-1 Hadrons, E > 1 GeV | |
1 | Single bunch - pilot | 5.0 x 109 | 14.0 | 4.0 x 108 | 1.0 x 10-4 | 9.0 x 103 |
2 | Single bunch - nominal | 1.0 x 1011 | 14.0 | 8.0 x 109 | 2.0 x 10-3 | 2.0 x 105 |
3 | Several (four) bunches - nominal | 4.0 x 1011 | 14.0 | 3.0 x 1010 | 7.5 x 10-3 | 7.0 x 105 |
5 | Maximum | 6.0 x 1013 | 18.0 | 4.0 x 1012 | 1.0 | 9.0 x 107 |
6 | TT40/TI8 tests | 2.5 x 1011 | 20.0 | 1.25 x 1010 | 3.0 x 10-3 | 3.0 x 105 |
Want access to their counting rooms during the test - fair enough. Interlocked Access door through their shielding wall should be in place.
DFW proposes that the first few hour(s) no access into LHCb counting rooms is granted to give RP time to control the prompt radiation levels in the counting room. Perhaps it would just be a "cosmetic" survey as we don't expect any radiation level - but we could check for (very) weak points in the shielding...Of course, we have fixed monitors installed but this survey I would like to be done in a more precise manner with technicians......After this survey and having found no surprise we could grant access immediately....
To my opinion this would be a decent RP approach - of course we have the results of our calculations - but nothing better than experimental, real data - they will be convincing....
"Under all circumstances we have to avoid tracing of equipment before we have circulating beams and therefore as well after the sector test. We can not trace all the equipment which will go in and out of the UX cavern during our commissioning phase which will end with the closing of our area in summer 2007. We might have still some temporary equipment which will leave the area after the injection test. INB implications on tracing from a supervised LHC area need to be established." Rolf Linder
Doris Forkel-Wirth:
About controlling material leaving LHC - I am convinced that after the sector test we will have to perform a radiological control of all material (including conventional) leaving the zone of the sector test.
About tracing ....no idea and I don't have any idea who decides on it - perhaps John Poole?
It might be that we have a major problem:
For people working in the LHC cavern it is only the dose rate at the workplace that counts. Hopefully we can convince IRSN that in case we will stay below one or two μSv/h, people will be permitted to work without dosimeters. However for the radiological classification of material (radioactive or conventional) the limits are much lower. In case Lindner wants to move his material we will have to ensure that e.g. the concentration of 60Co is below 1 Bq/g or better 0.1 Bq/g in his material........According to the Swiss legislation, material has to be considered as radioactive when the dose rate measured in 10 cm distance is above 0.1 uSv/h (after subtraction of the background). You see the problem?
The new French law (31 March 2003) keeps the classification of radiation workers of B and A - but the only difference is just the yearly dose limit (6 mSv - 20 mSv). There is no difference foreseen in the law with respect to medical control.
Given the removal of the temporary access gates, the TED etc. the main knock-on effect will be the declaration of the zone around the dump position and the injection region as supervised areas. Supervised areas imply:
During the test:
Prohibited area stretching from ECA4 to the interlocked gate close to point 6.
Monitors will be installed close to the gates in direction of point 6 and point
1. Additional RAMSES monitoring in LHC-b experimental cavern. Ventilation system
equipped with radiation monitors. Installation of Beam loss monitors, beam
intensity monitors and pick-ups….necessary. Access prevention from Point 7 and
Point 8.
After the test :
Supervised area (with exception of LHC-b experimental cavern) stretching
from ECA4 to the area where the temporary TED will be installed. Behind the TED
fencing of the area such, that on the other site the dose limit of 0.5 mSv/h
will be kept. Film badge obligatory in the supervised area, no passage
permitted for persons without film badge. It might be that some accelerator
components will have to be fenced off for some time immediately after the test.
According to the information acquired I would propose to the French authorities DGSNR the following for the LHC sector tests:
Assuming that the persons are not working in the zone but just trespassing it (temporary stay):
1) Classification of the zones according to dose rates.
2) After the tests we will do the radiation survey and depending on the outcome we will either proof: the dose rate in the zone are comparable
to those in a surveilled zone (< 2.5 microSv/h) -> we will declassify the zone as a surveilled one. The persons intervening into this zone don't
need any dosemeter nor medical clearance
3) In case the dose rate will be above 2.5 but below 10 microSv we will be most probably permitted to send "non-classified workers (neither A
or B) temporarily" into this zone. However, we have to verify the doses (electronic
dosimeter or visitor film badge). And we have to make sure
that the dose of such a person stays well below 1 mSv/year. No medial clearance would be required.
This proposal will have to be checked by DGSNR and hopefully approved - but parts of the French law are still under revision.
Doris Forkel-Wirth