Phase | When | ||
1 | Monday am | Extraction - TI2 - Injection - RF -BIS - timing - injection sequencer | See Bren's list |
1b | Monday pm | TDI, TCDD | |
2 | Monday pm | LHC beam instrumention - system by system
|
|
3 | Tuesday am | LSA settings check
|
|
5 | Tuesday | Power converter access, monitoring, SOC, logging etc. |
Check: Triggered data acquisition, logging, fixed displays, application (control,settings), equip state,
Status | Who | |
SDDS - acquistion and monitoring either via Triggered Data Acquisition or SBS logging LHC RING: BPMs, BLMs, Screens, BCT |
Greg Romain/Delphine/Nicolas |
System | What | Status | Who |
Beam Loss Monitors | Acquisition - CMW, subscription, concentration, republish for monitors involved | Done | Marek |
FD - histogram - etc. Bespoke display for standard control use - configurable - select monitors - history etc.- | In place | Fabio | |
Expert application: detailed look at acquired data. Timed acquistion - read buffer - software trigger | Check with Bernd | ||
Specialized application for BLM threshold management and adjustment - MCS [won't be used in sector test but should test]. Also test procedures - removal of beam permit etc. | Done - ready to test |
Greg | |
Study buffer - trigger on injection event & application (Fabio) |
|||
Beam Position Monitors | "Beam Threading" acquisition & concentration from each BPM crate involved. | Marek | |
Fixed Display - used standard ulitiies | YASP | ||
Trajectory: threading,
correction etc. etc. plus associated tools, harmonic analysis etc. etc
(mostly done already) Check corrector cc & trim checks |
Re-test | Jorg/YASP & LSA support |
|
Beam Current Transformer | Acquisition | OK | Markus |
Display | OK | Markus | |
BTV | Acquisition - SDDS etc. | OK | Greg |
Screen control | OK | standard LSA | |
Application | OK | Guy/Fabio | |
Beam Synchronous Timing | Not visible at high level - we hope [BI's group's responsibility) | - | |
Radmon - Thijs | Acquisition & Monitor Gateways covering Q5.L2 to IP3.R available week 30 (cfc-sr-sl2a, cfc-sr2-sr2b, cfc-sr3-st3a) c/o Anna Nyul |
Check | |
Leave concentration | |||
Display & logging (SIMA variables there) Alarms |
Equip monitor | Greg/Cyril Nicolas - logging |
What | When | Who | ||
Injection Kickers | State control settings & trim & timing - application |
Phase 1 | version in place Fixed display there (Markus) |
GHH |
Analogue Acquisition (plus beam) | Standard interface | Looks OK | Oasis | |
Septa | trim in terms of strength - trim interface | Phase 1 | Check | |
Functions - standard muGef | Check | - | ||
Timing | Check | - | ||
Monitoring - to be defined | Check | |||
TDI | Application - settings generation - as for collimators -in & out | Phase 1b | For HWC | Stefano |
TCCD | Monitoring | |||
Power Converters | Standard high-level control functionality: cycle, ramp, set, trim, states, tolerances Full funcitonality already in place for HWC |
Week 32 | Mike/Delphine | |
Magnets |
|
FIDEL | Check through all circuits | Luca/Mike/Marek S/Nicholas Sammut |
Pre-cycle prescription for all magnets available |
Extend | Check through all circuits | Lasse/Mike |
Task | What | Status | Who? |
Timeslice of functions, actual settings etc | done | Wojtek | |
Actual make rules | done | Lasse/Mike/Delphine | |
Incorporation | new version to test | Raphael | |
Optics, Twiss transfer - new optics for TI2 to load | done | Marek | |
Full operational cycle - nominal generation - all multipoles etc | Check! | Lasse/Mike/Delphine | |
Kickers, Septa, No ramping - should be simple |
check | Delphine/Stefano/Mike | |
Transfer function, harmonics | check | Marek/Mike |
What | Status | Who | |
Trim functionality - already in place - some extensions - testing | Wojtek | ||
Trim discrete settings | Wojtek | ||
Septa in terms of strength - makerule | Mike | ||
Bumps through septa - | YASP | ||
Crossing angle, separation bumps | YASP | ||
Phase advance | YASP | ||
Trim actual settings GUI | One day! | Markus | |
Trim LHC momentum | Marek S |
Ilya/Frank/Jutta - work in progress - basics for on-line model
Test | Who | |
Task: create actual settings | Week 31 | Reyes |
Task: set all power converters | ||
Task: sequence injection requests - interface with CBCM | ||
Task: maintain mode and distribute mode change | ||
Software start, injection requests etc etc |
Task | Who | |
Interface to timing system: |
Done | Delphine |
Transfer synchronization: pre-pulses | Andy | |
Diagnostics | ? |
Display | Resources |
|
Markus. Using standard facilites hopefully. Should be a matter of configuration - weeks plus support |
Run control from sequencer - OK
Not strictly required. Test with BLM thresholds. Verena leading charge. Will use sub-set of LSA functionality. NOT DURING TEST.
Should be tested - should not get in the way of the test - check. Leave it.
Power permit and abort (PICs) will need to be in place. WIC. Alice. Vacuum.
Extraction permit.
PBF
Transfer line interlocks will need to be in place.
Intensity transfer interlock.
What are we monitoring? Jorg, Jakob
Transfer line - everything
MKI Soft start
LHC PC state, SD currents
OK - clock the fill number - Wojtek!
Take as given the standard facilities for all systems.
Work in progress - ML August 08