Present: Helmut Burkhardt, Verena Kain, Brennan Goddard, Roger Bailey, Mike Lamont (chair), Jan Uythoven, Stephen Jackson, Rhodri Jones, Roberto Saban, Katy Foraz, Esther Barbero Soto.
ML presented a brief summary of the issues of the sector test vis a vis hardware commissioning and installation.
Date | Action | Comment |
Wednesday 15th - Friday 17th November | Installation of TED - point 7 | Access through 7-8 inhibited |
Thursday 23rd November | Close point 8, sector 7-8, sector 6-7 | Access system qualification. Control from CCC. |
Friday 24th November | TI8 test with beam | Machine remains closed over weekend - final machine checkout |
Monday 27th November - Sunday 10th December |
Sector test with beam | Access as required through point 8 |
Monday 11th December | Radiation Survey | No general access |
More details here
Installation – what needn’t be there
Given the list above there is little room for reduction on the installation front
Installation – what can’t be there
The temporary installation of the dump in IR7 implies the following constraints for the injection test:
Installation – temporary installation
Restricted to point 7:
Installation - ongoing in the rest of ring
The main impact of the test on installation is its effects on ongoing installation elsewhere. The test will limit:
Installation afterwards
Given the removal of the temporary access gates, the TED etc. the main knock-on effect will be the declaration of the zone around the dump position and the injection region as supervised areas. Supervised areas imply:
The required hardware and circuits are described here
Given the assumed schedule it is clear that the nominal 3 months of power tests requested for full hardware commissioning of sector 7-8 will be severely squeezed if the sector test is to take place as planned.
A discussion of about the possibilities of staging the HWC to meet the direct requirements of the sector test took place. It was noted that:
Action: The hardware commissioning team will establish the minimum possible time required to commissioned the required hardware to the necessary levels.
Also noted:
Hand over to operations
Also discussed was the potential handover of the sector to the operations group for machine checkout and access control.
It's clear that the test will remain a collaborative effort throughout the test with support of the HWC required for the duration. However, because of safety issues etc. a formal handover of responsibilities will be required. It was also noted that a dedicated machine checkout period is necessary; coordinated by operations from the CCC. Exact dates to be established.