Last update 16:00 Saturday August 23
Time | Phase | Resp | Approx elapsed time |
---|---|---|---|
Monday 18/Tuesday 19 | Dry Run | ||
Tuesday - Thursday | Magnet tests - S78 and 81- as available - PGC tests first | ||
Tuesday | Final tests with LHCb | ||
Thursday - Fri | The patrol will take place, during working hours, on Thursday 21 August and/or Friday 22 August. |
Laurette/Rossano | |
Friday pm | Access system - Beam ON | ||
14:00 - 15:00 | Access intrusion/LBDS tests | Thomas Ladzinski Brennan Goddard |
1 hour |
15:00 - 16:00 | Final prep of TI8 and EIS, final beam interlock tests |
Rossano, Bruno/Ben | 1 hour |
16:00 |
|
OP | 1 hour checks - trajectory etc. |
~17:00 |
|
INJ TEAM | 1 hour |
~18:00 | TDI out - threading - momentum matching - beam to IR7. | Jorg & team | 3 hours |
Over night Fri-Sat | Kick-response measurements, optics checks (no preemptive aperture checks) Take response data across end TI8 and p8 injection region using last corrector in TI8 |
Jorg & team | 8 hours |
Fri-Sat | Dispersion measurement Measurement of dispersion function at end of TI8 and across injection region |
Verena | |
08:00 | re-cycle |
1 hour | |
09:00 | Meeting | ||
Sat am | BPM system - capture mode, intensity dependence Timing-in without beam of LBDS system in inject and dump mode - parasitic - (for a quiet moment) |
Rhodri, Lars Bren |
3 hours |
re-cycle S78 | |||
Saturday evening/overnight | Gentle aperture measurements combined with beam through IR7, BLM response IR7 re-check optics if required. Dispersion measurement through IR7 Injection screen measurements in parasitic mode (VK) |
Stefano & co Bernd & co |
8-10 hours |
09:00 | Switch to TI2, re-cycle | ||
Sun. (finally started 15:00 going to take 4 hours minimum) |
SECTOR 23 revisited - dispersion through IR3 (increased intensity)- kick response revisited [2 10^9 into a magnet] |
Ops | 6 hours ALICE is informed that TI2 injection to point 3 will take place this week-end, on saturday, from about 14:00 to 19:00, with probably little time spent on TED and TDI (<20 min) and using first 2e9 probes then possibly 5e9 probes for the actual optics measurements. |
Back to S78 | |||
Sunday evening 19:00 | Finish Polarity checks etc |
Frank & Mike & co | 5 hours |
21:00 | Phase advance with trimmed main quads | John Jowett | 3 hours |
23:00 | Re-cycle - reset | ||
Sun night | Injection region aperture checks (3 hours) Measurement of MKI waveform using beam position response on injection screens - dedicated measurement with TDI closed to 'protect' setting (2 hours) |
Bren & team | 4-6 hours |
06:00 | End test | ||
08:00 | Start radiation survey, establish zones (areas which have seen beam) | RP | All day Monday |