Last update 16:00 Saturday August 23
| Time | Phase | Resp | Approx elapsed time | 
|---|---|---|---|
| Monday 18/Tuesday 19 | Dry Run | ||
| Tuesday - Thursday | Magnet tests - S78 and 81- as available - PGC tests first | ||
| Tuesday | Final tests with LHCb | ||
| Thursday - Fri | The patrol will take place, during working hours, on Thursday 21 August and/or Friday 22 August.  | 
    Laurette/Rossano | |
| Friday pm | Access system - Beam ON | ||
| 14:00 - 15:00 | Access intrusion/LBDS tests | Thomas Ladzinski Brennan Goddard  | 
    1 hour | 
| 15:00 - 16:00 | Final prep of TI8 and EIS, final beam interlock tests  | 
    Rossano, Bruno/Ben | 1 hour | 
| 16:00 | 
  | 
    OP | 1 hour checks - trajectory etc. | 
| ~17:00 | 
  | 
    INJ TEAM | 1 hour | 
| ~18:00 | TDI out - threading - momentum matching - beam to IR7. | Jorg & team | 3 hours | 
| Over night Fri-Sat | Kick-response measurements, optics checks (no preemptive aperture checks) Take response data across end TI8 and p8 injection region using last corrector in TI8  | 
    Jorg & team | 8 hours | 
| Fri-Sat | Dispersion measurement Measurement of dispersion function at end of TI8 and across injection region  | 
    Verena | |
| 08:00 | re-cycle  | 
    1 hour | |
| 09:00 | Meeting | ||
| Sat am | BPM system - capture mode, intensity dependence Timing-in without beam of LBDS system in inject and dump mode - parasitic - (for a quiet moment)  | 
    Rhodri, Lars Bren  | 
    3 hours | 
| re-cycle S78 | |||
| Saturday evening/overnight | Gentle aperture measurements combined with beam through IR7, BLM response IR7 re-check optics if required. Dispersion measurement through IR7 Injection screen measurements in parasitic mode (VK)  | 
    Stefano & co Bernd & co  | 
    8-10 hours | 
| 09:00 | Switch to TI2, re-cycle | ||
Sun. (finally started 15:00 going to take 4 hours minimum)  | 
    SECTOR 23 revisited  - dispersion through IR3 (increased intensity)- kick response revisited  [2 10^9 into a magnet]  | 
    Ops | 6 hours ALICE is informed that TI2 injection to point 3 will take place this week-end, on saturday, from about 14:00 to 19:00, with probably little time spent on TED and TDI (<20 min) and using first 2e9 probes then possibly 5e9 probes for the actual optics measurements.  | 
  
| Back to S78 | |||
| Sunday evening 19:00 | Finish Polarity checks etc  | 
    Frank & Mike & co | 5 hours | 
| 21:00 | Phase advance with trimmed main quads | John Jowett | 3 hours | 
| 23:00 | Re-cycle - reset | ||
| Sun night | Injection region aperture checks (3 hours) Measurement of MKI waveform using beam position response on injection screens - dedicated measurement with TDI closed to 'protect' setting (2 hours)  | 
    Bren & team | 4-6 hours | 
| 06:00 | End test | ||
| 08:00 | Start radiation survey, establish zones (areas which have seen beam) | RP | All day Monday |