See this also as dry run for taking beam on Wednesday 10th - full machine closed.
Time | Phase | Resp | Approx elapsed time |
---|---|---|---|
Monday 1/Tuesday 2 | Dry Run Things should be in a reasonable good shape following previous tests. All circuits required have been available. | OP | |
Friday | Machine should have been patrolled. Difference this time is CMS should vacate their cavern and patrol. |
Laurette/Rossano | |
Friday pm | Access system - Beam ON | ||
Friday pm | Final prep of TI8/12, EIS, final beam interlock tests. Time for LBDS arming and sequencer tests with full permit loop (could take longer this time, everything now in the loop). |
Rossano, Bruno/Ben, Etienne | 3 hours |
Friday pm |
|
OP | 1 hour checks - trajectory etc. |
Friday pm |
|
INJ TEAM | 1 hour |
Friday pm | TDI out - threading - beam to IR7 - correct. | Jorg & team | 3 hours |
Late Friday pm | Collimators out - LBDS inject and dump set at >1 turn - thread beam to point 6 - steer into beam dump channel using orbit correctors - first check dump line instrumentation. | OP - BT | |
Late Friday | Dispersion measurements and investigations and measurements for dispersion and matching at the end of TI 8 (trims and rematching if necessary) | Malika & team | 8 hours |
Over night Fri-Sat | Kick-response measurements, optics checks (no preemptive aperture checks) Take response data across end TI8 and p8 injection region using last corrector in TI8. |
Jorg & team | |
08:00 | Enable Beam Dump Kicker - first try at inject and dump |
Etienne | 1 hour |
09:00 | Meeting | ||
Saturday 09:00 - 16:00 | Cryo 8 down - access - recovery |
||
18:00 | Beam through Alice - screens SECTOR 23 revisited - check Alice's multiplicity with screens out. |
||
Evening | Collimator studies point 3 | Ralph | |
Overnight - | Polarity //TI8 measurements |
|
8-10 hours |
Sunday 08:00 | Foresee access into CMS for vacuum pump-down checks |
Adriana, Ray
|
2 hours |
Sun. am |
Reproducibility |
Mike, Luca, et al | 4 hours
|
Sunday midday | Cryo point 8 back - possible | ||
Sun afternoon | Full machine dry run - pre-cycle, set and trim etc, | OP | 6 hours |
Sunday late - if S78 back | Commission beam dump region - extract with beam dump kickers - set of measurements with extracted beam - some checks also proposed with beam onto TCDQ (feasible?) Details here |
Bren and team |
8 hours |
TI8/ LHC dispersion measurments continued | |||
Overnight Sun/Mon | Polarity checks - consolidation if required. | Frank & team | 6 hours |
06:00 | End test | ||
08:00 | Radiaton survey - point 6 | Doris Forkel-Wirth | |
08:30 | Controls database stop - 20 minute intervention | Ronny Billen |