Sector Test Meetings

 

Date Subject
02-09-2008 Prep for test 3
26-08-2008 Results from test 2
12-08-2008 Results from first sector test - preparation for second injection test
22-07-2008 Injection test 9/10 August 2008 - matters arising - beam interlocks - beam instrumentation
11-07-2008 Sector test 2008 - injection point - dump on collimators IR3 - planned date 2/3 August 2008
02-05-2006 Sector test 2007
31-01-2006 Measurement procedures
07-12-2005 Installation and Hardware Commissioning
29-11-2005 Beam Position Monitors
15-11-2005 Beam Loss Monitors - Quenches - ABP involvement
01-11-2005 Access  - schedule - Chamonix XV
07-10-2005 INB follow-up, planned tests with beam - review
02-09-2005 INB documentation,  IR7
17-06-2005 General Issues
06-04-2004 Access system
23-03-2004 Quenches with beam
07-10-2004 Combined meeting with TI8  Access/radiation